The Phobition Reason
There are some critical reminding which shall be reminded again.
If the equipment shall be released and delivered to the site, vendor shall get the permit and approval from the client.
Otherwise, manufacturing and shipping are not acceptable.
As following items shall be fully completed.
1. Submittal document to get approval.
We need to get the approval for each design document 1 month before delivery.
If there is any document not yet to get the approval from TPC, the equipment shall be prohibited to release to delivery to the site.
That’s why I keep reminding you to submit the document. Every week’s reminding is not merely the reminding, it also means the record to record the pending situation.
Please expedite your design drawing’s and document’s submitted situation.
2. Inspection’s approval
IQP(Individual Quality Plan) is the foundation that make TPC to recognize whether the equipment can be inspected and tested.
Also, ITP is the base to define whether to witness or report as per specification and TPC’s comment.
Until IQP to define as approval(not only AEN), then vendor can start acting inspection and test.
Note: Motor is the main item to witness. (7.5KW and above for local; 187KW and above for oversea)
3. Material Certificate and Material Mill Test Report.
Material Certificate and Material Mill Test Report definitely shall be submitted to Client to get the approval before Shop Test.
If the certificate and report does not be get the approval by client, the manufacture is absolutely prohibited, which will influence the further inspection.
Liquidation and penalty fine is not the only method will be executed, but the equipment cannot be accepted to release and delivery is also the key point reason.
Please pay more attention on Submittal Document, Inspection and Material.